Wrightwood’s public restroom renovation is finally underway, bringing the community closer to improved facilities for residents and the visitors who flock to the village throughout the year.
The project, located near the Wrightwood Community Building and Vivian Null Park at 1275 Highway 2, addresses a recurring challenge for Wrightwood, where visitor surge following winter snowstorms. The existing facilities have struggled to accommodate peak demand during the winter, prompting the district to arrange portable restrooms.
Back in 2024 The Wrightwood Community Services District (WCSD) accepted a grant from San Bernardino County to improve the public restrooms. However, the project faced significant financial challenges before construction could begin.
The original concept called for renovating the existing restrooms and expanding the facilities by converting a nearby building, adding approximately 400 square feet of restroom space. Preliminary estimates for the proposed project exceeded $1 million, well above the $350,000 grant awarded through San Bernardino County’s Discretionary Fund Priorities Program, which supports local infrastructure projects.
The WCSD ultimately revised the project’s scope to focus on renovating the existing restrooms rather than converting an additional building. The change was discussed at the district’s Nov. 4, 2025, regular meeting. Project updates and a contract amendment with San Bernardino County followed in December 2025, incorporating improvements that included an additional toilet, insulation, heating, ventilation and accessibility features.
The district’s original grant award was previously reported by NewsPlus in “WCSD Secures Grant for Village Restroom Expansion.”
The WCSD also addressed accessibility improvements that were not covered by the grant. During the WCSD April 21, 2026, meeting, the board unanimously voted to set aside $78,528 in district funds to support ADA accessibility upgrades.
While the project is funded largely through the county grant, the additional allocation allows the district’s commitment to address accessibility needs beyond those covered by the grant-funded construction.
Finally at the WCSD Sept. 1, 2026, meeting, the board awarded the construction contract to Bridge Rock Construction, which submitted the lowest responsive bid at $318,000.
The district maintains a grant savings account for the Bathroom Renovation Project, which had a budget of $329,565.56 available for construction. The available funds were sufficient to cover the anticipated construction cost, so no additional funding source was required for the construction portion of the project. Additional funds were also been set aside to address any potential contingencies that arise.
Construction began mid-September and the project is progressing toward its anticipated completion in early December. In fact, during the WCSD’s Oct. 6 meeting, district President Dave Schoenwetter reported that demolition had progressed quickly.

“So, if you’ve looked outside behind the green wall, the restroom project is well underway,” Schoenwetter said. “We were here on day one. Our meeting was at 9 or 9:30, and the entire interiors had been demolished within those first three hours. So, as a reminder, it’s a complete rehab with ADA accessibility upgrades, and things are moving quickly.”
With a tight construction timeline, the WCSD is holding weekly Wednesday morning meetings to monitor development and help keep the project on schedule.
The Restroom Ad-Hoc Committee includes Schoenwetter and Director Rick Christenson. The committee meets with Project Manager Todd Mortensen of CPM, WCSD Interim General Manager Angela Rovida and the contractor from Bridge Rock Construction to review progress and finalize work.
With demolition complete and construction advancing, the renovation marks a significant step toward improving public facilities in Wrightwood. The district expects the renovated restrooms to be ready by early December, during the heart of the busy winter season.